General Aviation Facility Requirements Calculations

DescriptionGA Terminal
• Calculate the minimum terminal space required by
FAA for Dekalb County Airport . The existing GA
terminal has 1,200 SF of space and there are currently
4 design hour operations and 5 pilots/passengers per
design hour operation on average. What are the
expansion requirements in the years 2025, 2030 and
2040 given the following forecast:
• 2025 – 5 design hour operations
• 2030 – 6 design hour operations
• 2040 – 7 design hour operations
Assume the average number of pilots/passengers per design
hour operation remains the same in the future.
What are your recommendations?
GA Terminal – Assignment #5
Row
Description
1
Design Hour Operations
2
Design Hour Passengers
3
Planning Parameter (SF)
4
Space Required (SF)
5
Existing Capacity (SF)
6
Facility Requirement (SF)
(Shortfall)/Surplus
Existing
(2020)
2025
2030
2040
Based Aircraft Storage
• Based on the following forecast for based aircraft at
Dekalb County Airport calculate the requirements for
based aircraft storage.
• Assume that 70% of SE aircraft, 80% 0f ME aircraft and
100% for turbine aircraft require conventional storage
space.
• In addition, 15% of SE and 10% of ME aircraft require Thangars.
• The existing facilities at the airport consists of 20 T-hangar
units and 300,000 SF of conventional hangar storage
space.
• What are the based aircraft storage requirements in the
years 2025, 2030 and 2040?
Based Aircraft Storage – Assignment #5
Based Aircraft
SE Aircraft
ME Aircraft
Turbine Aircraft
Existing
100
40
10
2025
120
60
15
2030
140
80
25
2040
180
120
40
Based Aircraft Storage
Year
T-Hangar Requirements
SE (___% of Demand)
ME (___% of Demand)
Total Demand
Existing T-Hangars
(Shortfall)/Surplus
Existing
2025
2030
2040
Based Aircraft Storage
Year
Existing
Conventional Storage Requirements
SE (___% of Demand)
Planning Parameter
SE Space Required (SF)
ME (___% of Demand)
Planning Parameter
ME Space Required (SF)
Turbine (___% of Demand)
Planning Parameter
Turbine Space Required (SF)
Total Space Required (SF)
Existing Space (SF)
(Shortfall)/Surplus (SF)
2025
2030
2040
Based Aircraft Apron
• Based on the following forecast for based aircraft at
Dekalb County Airport calculate the requirements for
based aircraft tie-down space.
• Given: 70% of SE aircraft, 80% 0f ME aircraft and 100% for
turbine aircraft require conventional storage space.
• Given: 15% of SE and 10% of ME aircraft require Thangars.
• Given: the remainder of the based SE and ME aircraft
require tie-down storage.
• The existing facilities at the airport provide 8,000 SY of tiedown apron space.
• What are the based aircraft tie-down apron requirements
in the years 2025, 2030 and 2040?
Based Aircraft Storage – Assignment #5
Based Aircraft
SE Aircraft
ME Aircraft
Turbine Aircraft
Existing
100
40
10
2025
120
60
15
2030
140
80
25
2040
180
120
40
Based Aircraft Apron
Year
SE (___% of Demand)
ME (___% of Demand)
Total Demand
Planning Parameter (SY)
Total Tie-down Apron Area
Required (SY)
Existing Tie-down Apron (SY)
(Shortfall)/Surplus
Existing
2025
2030
2040
GA Vehicular Parking
• Calculate the vehicular parking space for Dekalb
County Airport . The existing GA terminal parking lot
has 11,200 SF of space and there are currently 4
design hour operations and 5 pilots/passengers per
design hour operation on average.
• What are the expansion requirements in the years
2015, 2020 and 2030 given the following forecast:
• 2025 – 5 design hour operations
• 2030 – 6 design hour operations
• 2040 – 7 design hour operations
Assume the average number of pilots/passengers per design
hour operation remains the same in the future.
GA Vehicular Parking – Assignment #5
Row
Description
1
Design Hour Operations
2
Design Hour Passengers
3
Number of spaces Required
4
Space Required (SF)
5
Existing Capacity (SF)
6
Facility Requirement (SF)
(Shortfall)/Surplus (Row 5Row 4)
Existing
(2020)
2025
2030
2040

Purchase answer to see full
attachment

We offer the bestcustom writing paper services. We have done this question before, we can also do it for you.

Why Choose Us

  • 100% non-plagiarized Papers
  • 24/7 /365 Service Available
  • Affordable Prices
  • Any Paper, Urgency, and Subject
  • Will complete your papers in 6 hours
  • On-time Delivery
  • Money-back and Privacy guarantees
  • Unlimited Amendments upon request
  • Satisfaction guarantee

How it Works

  • Click on the “Place Order” tab at the top menu or “Order Now” icon at the bottom and a new page will appear with an order form to be filled.
  • Fill in your paper’s requirements in the "PAPER DETAILS" section.
  • Fill in your paper’s academic level, deadline, and the required number of pages from the drop-down menus.
  • Click “CREATE ACCOUNT & SIGN IN” to enter your registration details and get an account with us for record-keeping and then, click on “PROCEED TO CHECKOUT” at the bottom of the page.
  • From there, the payment sections will show, follow the guided payment process and your order will be available for our writing team to work on it.